In 2019, MiningStore partered up with the Grundy Center Rural Electric Co-Op to construct a state-of-the-art bitcoin mining facility to their electric substation located in Grundy Center, Iowa. The project began with the deployment of a 1-megawatt mining container which was repurposed from our BioStar Renewables solar farm deployment. After the container was shipped and delivered, MiningStore’s techs quickly energized the container which functions as one of our many hosting options for our valued clients.
The one-megatt container houses over 600 S9 bitcoin miners for our clients. After the 2020 bitcoin halving we intend to repurpose the container to be fitted with new generation mining servers.
After the successful installation of the first one-megawatt bitcoin mining container, MiningStore continued on to deploy a 2.2-megawatt bitcoin mining container that was also purposed for customer hosting. This container houses a mix of new and old generation machines for our clients.Â