Case Study
What We Learned Replacing a Pump Motor in a Hydro-Cooled HK3 Deployment
Field Report from MiningStore Technicians
Overview:
During a recent deployment of a hydro-cooled mining site using the AntSpace HK3 V2 container, our team encountered a major delay caused by a mismatch in pump motor wiring.
Although the replacement motor matched spec sheet voltage and power ratings, it was shipped in a Delta configuration, while the HK3 requires a Wye (Star) configuration for correct integration with its soft-start, overload, and phase protection systems.
The spec sheet didn’t disclose the internal wiring, and like many operators would, we assumed the unit would ship in Wye like the original.
What Went Wrong:
- The motor arrived wired in Delta (∆)
- The HK3 expects a Wye (Y) configuration
- HK3 electrical cabinet failed to start the motor
- Phase imbalance caused protection circuits to trip
- We had no wiring diagram, just a label with incomplete data
- Coordination delays with the supplier added hours of install downtime


How to Identify the Wiring Configuration (in the field):
- Look at the terminal box:
- Delta wiring will have jumpers across L1-L2, L2-L3, L3-L1
- Wye will have one side (U2/V2/W2) joined together (common neutral)
- Use a multimeter for continuity checks
- Tone out windings and map them (e.g., U1-U2, V1-V2, W1-W2)
- Watch for three groups of windings: each should be independent
How We Rewired the Motor (on-site):
- Verified motor winding pairs using resistance/continuity testing
- Removed Delta jumpers across phases
- Joined the neutral ends (U2, V2, W2) for a Wye center point
- Reconnected U1, V1, W1 to L1, L2, L3 from the HK3 power bus
- Verified phasing and startup torque with slow ramp-up via HK3 soft starter
Important: This should only be done by a qualified technician. Improper rewiring can cause damage to the HK3 soft-start module or the motor itself.

Pre-Procurement Checklist We Now Use:
Question | Why It Matters | What to Ask the Supplier |
---|---|---|
Is this motor wired for Wye (Star) by default? | Request internal wiring diagram before ordering | Replace coolant if pH < 7 |
Can you provide the wiring diagram and torque curve? | Confirms startup behavior and compatibility with HK3 soft starter | Ask for the OEM wiring sheet and torque specs |
What’s the inrush current and phase feedback behavior? | Prevents tripping HK3 soft-start protection or triggering phase imbalance alarms | Ask for full nameplate electrical parameters |
Does this motor match the HK3 cabinet overload settings? | To avoid nuisance trips or permanent hardware damage | Share HK3 specs with vendor and request compatibility confirmation |
Key Takeaways (Technician-Focused):
- Never assume wiring configuration, confirm it.
- Even if it’s “identical specs,” you must validate wiring and phase compatibility.
- Request supplier documentation early.
- Don’t wait until delivery to discover wiring mismatches.
- Always ask for internal schematic, not just the front page spec sheet.
- Keep a visual wiring reference on-site.
- Diagrams showing Wye vs. Delta help field teams validate what’s in the box.
- Treat every replacement part like a custom integration.
- Even one wrong assumption adds risk, time, and potential damage.
Final Thoughts:
This incident underscores a crucial truth in hydro-cooled mining deployments: even seemingly minor technical discrepancies can translate into significant delays, lost hashrate, and mounting costs. Since then, we’ve formalized a Motor + Pump Pre-Check SOP, built vendor checklists, and added redundancy plans for container-level commissioning.
While meticulous planning and comprehensive checklists are vital, the dynamic nature of large-scale setups, especially with specific hardware like the HK3, often presents unforeseen challenges.
Why let a single wiring mismatch, or any other overlooked detail, push your deployment timeline back weeks?
Our specialized team not only anticipates these complexities but possesses the field-proven experience to navigate them swiftly, ensuring your hydro mining operation is up and running at peak efficiency, exactly when you need it.
Don’t just avoid pitfalls; accelerate your path to profitability with a partner who understands every nuance of hydro deployment. Let us eliminate the unknowns and bring your hydro vision to life, faster and flawlessly.